The risk-register skill assists project teams in identifying, documenting, and prioritizing risks. It employs a qualitative Probability x Impact (P x I) assessment methodology to score risks, helping teams focus on high-priority threats. The skill produces standardized documentation, including a detailed risk register and a corresponding mitigation plan, ensuring that risks are categorized, assigned owners, and supported by actionable contingency strategies.
What it does
- Creates a structured risk register in Markdown format.
- Applies a qualitative P x I matrix to score and rank project risks.
- Generates a dedicated risk mitigation plan for high-priority items.
- Standardizes risk documentation with clear Cause-Event-Impact statements.
- Organizes all outputs into a dedicated project documentation folder.
- Facilitates the assignment of risk owners and trigger events.
When to use it
- During the initial planning phase of a new project.
- When a project requires a formal, structured approach to risk management.
- When teams need to identify and prioritize technical or operational uncertainties.
- When preparing for project audits or stakeholder status reviews.
Advantages
- Promotes consistent risk assessment across the project team.
- Ensures high-impact risks are prioritized for mitigation.
- Provides a clear, readable format for stakeholder communication.
- Encourages proactive contingency planning rather than reactive management.
Usage examples
- “Create a risk register for our new cloud migration project.”
- The agent will prompt for project details and then generate a risk-register.md and risk-mitigation-plan.md in the docs/risks/ folder.
- “Generate a risk assessment for the upcoming API integration milestone.”
- The agent will focus on risks specific to the API integration, scoring them by probability and impact, and listing them in a prioritized table.
Install
Download the skill as a ZIP:
https://autogineer.com/agent-skills/microsoft/risk-register/downloadUnzip it into the cross-client skills folder of your project:
mkdir -p .agents/skills && unzip risk-register.zip -d .agents/skills
Documentation by Microsoft
Risk Register Generator
[!CAUTION] This skill is an assistive tool only and does not replace professional security and risk management tooling or qualified human review. All generated risk registers, risk scores, and mitigation strategies must be reviewed and validated by qualified security and risk professionals before use. AI outputs may contain inaccuracies, miss critical risks, or produce assessments that are incomplete or inappropriate for your environment.
Purpose and Role
Act as a risk management assistant. Help the user identify, document, and prioritize project risks using a qualitative risk assessment approach based on a Probability × Impact (P×I) risk matrix.
Use clear, simple, professional language and avoid unnecessary detail. Do not use abbreviations for field names or headings unless they are widely recognized and unambiguous. Place all outputs in the docs/risks/ folder.
Inputs
project-name(optional): Project name used for context and, in multi-project repositories, file naming.focus-area(optional): Risk focus area, domain, component, milestone, or concern to emphasize.
Step 1: Gather Project Context
If not already available in the repository, ask the user to provide:
Project name and short description.
Timeline and key milestones.
Stakeholders and dependencies.
Technical components or systems involved.
Known risks or concerns.
Sources of uncertainty.
Assessment of potential consequences related to project objectives.
Step 2: Prepare Risk Documentation Structure
Ensure the folder
docs/risks/exists. Create it if missing.Place all generated files inside the
docs/risks/folder.Use clear and direct file names and headings.
File naming conventions:
Primary register:
risk-register.md.Versioned register snapshot:
risk-register-YYYY-MM-DD.md.Mitigation plan:
risk-mitigation-plan.md.Multi-project repository register:
risk-register-[project-name].md.
Step 3: Create risk-register.md in docs/risks/
Include these sections:
Executive Summary.
Project Overview.
Risk Assessment Methodology.
Overview Table of Risks.
Detailed Risk Entries.
Risk Assessment Methodology
Document this methodology in the register:
Risks are scored using a P×I matrix with qualitative bands (Low, Medium, High) for both Probability and Impact.
Default Probability scale:
Low: unlikely.
Medium: possible.
High: likely.
Default Impact scale:
Low: minor effect.
Medium: moderate effect.
High: major effect.
Risk Score (Qualitative) = Probability × Impact using qualitative labels, such as High × Medium.
Risk Score (Numeric) converts qualitative ratings to numbers for sorting:
Low = 1.
Medium = 2.
High = 3.
Example: High × Medium = 3 × 2 = 6.
Document rationale for each rating in 1 to 2 lines for consistency.
Overview Table of Risks
Use these columns:
Risk ID.
Risk Title.
Description (Cause → Event → Impact).
Probability (Low, Medium, High).
Impact (Low, Medium, High).
Risk Score (Qualitative) = Probability × Impact, such as High × Medium.
Risk Score (Numeric) = Numeric value for sorting, such as 6.
Example:
| Risk ID | Risk Title | Description (Cause → Event → Impact) | Probability | Impact | Risk Score (Qualitative) | Risk Score (Numeric) |
|---|---|---|---|---|---|---|
| R-001 | API rate limits exceeded | High request volume without effective throttling → API rate limits are exceeded → Requests fail and downstream workflows degrade | High | Medium | High × Medium | 6 |
| R-002 | Key developer unavailable | Single point of knowledge in a key area → Key developer becomes unavailable → Delivery slows and defects increase | Medium | High | Medium × High | 6 |
| R-003 | Third-party service outage | Dependency on an external provider → Third-party service becomes unavailable → Features relying on it fail and user experience degrades | Medium | Medium | Medium × Medium | 4 |
Detailed Risk Entries
Include these fields for each risk:
Risk ID and Title.
Description (Cause → Event → Impact).
Probability and Impact ratings plus rationale.
Risk Score (Qualitative) = Probability × Impact, such as High × Medium.
Risk Score (Numeric), such as 6.
Category.
Mitigation Strategy.
Contingency Plan.
Trigger Events.
Owner.
Status.
Use short, focused descriptions. Avoid jargon and unnecessary elaboration. Sort all risks by descending Risk Score (Numeric) to highlight the most critical risks.
Step 4: Create risk-mitigation-plan.md in docs/risks/
Base the mitigation plan on the mitigation strategies already defined in risk-register.md. Focus on the highest priority risks, especially those with high probability and high impact, and summarize the planned responses.
Use this outline:
Top Priority Risks (High Uncertainty and High Consequence).
Risk Response Actions derived from mitigation strategies in
risk-register.md.Resource Requirements.
Communication Plan.
Risk Reassessment Schedule.
Guidelines
Use Cause → Event → Impact format for risk statements.
Define and document qualitative scales upfront.
Record rationale for each rating.
Include trigger events and assign a single accountable owner per risk.
Establish reassessment cadence and closure criteria.
Use clear, concise, and simple language throughout all sections.
Avoid unnecessary detail or verbosity.
Avoid abbreviations for field names or headings, for example use "Priority" instead of "P", unless they are widely recognized and unambiguous.
Include both technical and non-technical risks.
Focus on actionable mitigation strategies.
Consider internal and external risk factors.
Stop Rules
Ask for missing project context when repository evidence and user input do not provide enough information to identify meaningful risks.
Stop before writing tracker-bound or externally visible risk artifacts outside
docs/risks/.Stop before treating generated risks, scores, or mitigations as final without qualified human review.
Success Criteria
docs/risks/contains the generated risk register and mitigation plan.The risk register defines the qualitative Probability × Impact scoring method and rating rationale.
The overview table and detailed entries use the required fields.
Risks are sorted by descending numeric score.
The mitigation plan is derived from the register and focuses on the highest priority risks.
Files
- ATTRIBUTION.mdAdded by AutoGineer831 B
- LICENSELicence file added by AutoGineer1.1 KiB
- SKILL.md7.2 KiB
Requirements and compatibility
Written for: GitHub Copilot, Claude Code
Works with: Claude Code, Claude apps, OpenAI Codex, GitHub Copilot, Cursor, Gemini CLI, Kiro, OpenCode, Goose, Amp, Roo Code, JetBrains Junie, Factory Droid, Devin (ex-Windsurf), Mistral Vibe, OpenHands, Letta
“Works with” means the tool reads the open Agent Skills format; a skill written for one tool may use features others lack.
Needs: Claude Code frontmatter
Security
No issues found by our static scan· No issues found
A static scan is not a guarantee. Skills are third-party content: review a skill before you let an agent use it.
Attribution and licence
- Published by
- Microsoft
- Publisher
- Microsoft (Official)
- Source
- microsoft/hve-core · .github/skills/security/risk-register · commit f425e94
- Licence
- MIT License (redistribution allowed)
- LICENSE (added by AutoGineer from LICENSE)
- ATTRIBUTION.md (written by AutoGineer)
- Synced
AutoGineer is not affiliated with or endorsed by Microsoft or Microsoft.
Download ZIP
The ZIP holds the skill’s files, its licence files and an ATTRIBUTION.md. Download risk-register.zip